Cabinet Clears Extra Tracks on India’s Crowded Rail Spines

Eight new railway lines add 1,196 km on coal and southern freight spines inside a 11,000 km four-tracking drive.

Published

on

India’s Cabinet on September 9, 2026 cleared eight railway multi-tracking projects worth ₹20,804 crore, adding 1,196 km on crowded freight spines. The work is due by 2029-30.

Railway Minister Ashwini Vaishnaw, briefing after the meeting, placed those eight jobs inside a larger file: four tracks on about 11,000 km of high-density corridors. About 2,000 km is already four-lined, about 5,000 km is approved or under way, and about 4,000 km is still in the last sanction stage.

The Eight Projects Sit on Two Overloaded Spines

The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, did not fund a scatter of new branch lines. It funded extra tracks on routes that already carry coal, steel, cement, boxes, cars and grain, planned under the PM-Gati Shakti National Master Plan.

Five jobs worth ₹10,021 crore add about 540 km across 17 districts in Tamil Nadu, Andhra Pradesh, Karnataka and Telangana. Three jobs worth ₹10,783 crore add about 656 km across 14 districts in West Bengal, Jharkhand, Odisha, Madhya Pradesh and Chhattisgarh. Together they cover 31 districts in nine states.

THE PACKAGE IN FIGURES

  • Extra freight: 74 million tonnes a year once both packages are in service, 47 million in the south and 27 million in the east.
  • Catchment: 6,911 villages with about 1.08 crore people (2,121 villages and 52 lakh people in the south; 4,790 villages and 56 lakh people in the east).
  • Oil and carbon: the south package is scored at about 8 crore litres of oil imports and 42 crore kg of carbon dioxide avoided; the east package at about 12 crore litres and 62 crore kg, equal to 2.48 crore trees.
  • Jobs on the eastern works: more than 223 lakh human-days, as put in the Cabinet briefing notes.

Two of the Tamil Nadu jobs are still doubling, which means a second line rather than a third or fourth. Multi-tracking here is a mix of catching up to two tracks and pushing the busiest trunks toward four.

THE EIGHT ROUTES CLEARED ON SEPTEMBER 9

Route Work Length Region
Kharagpur-Jharsuguda (Bagdehi) Fourth line 367 km East-central
Katni-Pendra Road Fourth line 201 km East-central
Bilaspur (Uslapur)-Pendra Road Third line 87 km East-central
Arakkonam-Renigunta Third and fourth lines 77 km South
Whitefield-Bangarapet Third and fourth lines 47 km South
Hosur-Omalur Doubling 147 km South
Salem-Karur-Dindigul Doubling 159 km South
Secunderabad (Ghatkesar)-Kazipet Multitracking 110 km South

Group lengths in the two government releases are 656 km and 540 km. The listed stretches sum one kilometre short of those round figures.

Howrah-Mumbai Already Runs Past 118 Percent

The largest single ticket is the Kharagpur-Jharsuguda (Bagdehi) fourth line, costed at ₹6,528 crore. It sits on the Howrah-Mumbai high-density route. Line use is already 118 percent, and briefing notes said that load could rise to 133 percent if the fourth line is not built.

That stretch is scored for 13.19 million tonnes of extra freight a year: 6.15 million tonnes of iron and steel, 3.41 million tonnes of coal and coke, 2.87 million tonnes of cement, and 0.76 million tonnes of other goods. Logistics savings are put at about ₹968 crore a year, with cargo from Haldia, Paradip and other eastern ports among the flows the extra track is meant to unstick.

The three eastern multi-tracking projects are written up as coal, cement, iron and steel routes, with 27 million tonnes of extra freight a year across the package. Katni-Pendra Road (201 km) links four Madhya Pradesh districts, Anuppur, Shahdol, Umaria and Katni, with Gaurela-Pendra-Marwahi in Chhattisgarh, on the Kota-Paradeep corridor. It is the land bridge from central India to South Eastern Coalfields Ltd pits at Korba, Gevra, Dipka, Kusmunda and Chirimiri, and onward to thermal plants in the north and west.

Bilaspur (Uslapur)-Pendra Road, an 87 km third line, covers Bilaspur and Gaurela-Pendra-Marwahi. Briefing notes tie it to steel and cement out of the Raipur-Bhilai belt and to the same north-and-west coal run. The zonal freight interchange at Jharsuguda is already treated inside the Railway Board as a detention point, with flyovers, extra lines and even private siding work listed against the junction.

Passenger trains on the Kharagpur-Bilaspur belt have been running hours late for years. Extra tracks are a reply to that grind, because on a two-line section the timetable still gives the express the path and the coal rake the siding.

In the case of double-laning of railway tracks, passenger trains get preferred and freight rakes including coal, do not get sufficient time and space for movement and therefore their average speed is extremely slow. With the increase in tracks to third and fourth lines, the rake and track availability for freight rakes having coal, cement, and other commodities will improve.

Amrit Lal Meena, former secretary, Union Ministry of Coal

That is also the older warning in energy research on coal’s crowding of trunk passenger paths: the same corridors cannot keep absorbing more colliery rakes unless the track count rises.

Southern Packages Chase Autos, Containers and IT Freight

The southern five are a different cargo mix. The Press Information Bureau lists coal, cement, iron and steel, then containers, automobiles, food grains, petroleum products and fertilisers, and scores the package for 47 million tonnes of extra freight a year.

Arakkonam-Renigunta, 77 km of third and fourth lines, is on the Mumbai-Chennai high-density corridor. Use is about 120 percent. Extra freight is put at 7.21 million tonnes a year, with logistics savings of about ₹110 crore. Whitefield-Bangarapet is only 47 km, yet it is scored for 14.53 million tonnes, the fattest freight add in the southern list, and about ₹137 crore in yearly logistics savings, at 105 percent use, with more load expected as nearby economic nodes grow.

Hosur-Omalur doubling (147 km) is put at 8.95 million tonnes and about ₹263 crore in yearly savings, the largest logistics figure in the south. Salem-Karur-Dindigul doubling (159 km) is put at 6.87 million tonnes and about ₹219 crore. Union Coal and Mines Minister G. Kishan Reddy said the 110 km Secunderabad (Ghatkesar)-Kazipet multitracking is costed at ₹2,208.69 crore. The PIB tourist list for the five jobs runs from Tirupati and Tiruttani through Kolar Gold Fields, Mettur Dam, the Kodaikanal hills and Sathyamangalam Wildlife Sanctuary to Yadagirigutta and Bhongir Fort.

Modi, posting after the meeting, said the five southern jobs would give South India better rail links, faster passenger movement and more freight room. The eastern three, he wrote, would add network in Chhattisgarh, Jharkhand, Madhya Pradesh, Odisha and West Bengal, help heritage and wildlife travel, and cut logistics costs.

Four-Tracking 11,000 km Is the Larger File

Vaishnaw has said the seven high-density routes span nearly 11,000 km and take about 41 percent of railway traffic while covering just 16 percent of the network. They are Delhi-Howrah, Howrah-Chennai, Chennai-Mumbai, Mumbai-Delhi, Delhi-Chennai, Mumbai-Howrah and Delhi-Guwahati, the Golden Quadrilateral plus its diagonals and the north-east trunk.

At the September 9 briefing he gave the build status in three buckets, which add up to the same 11,000 km.

In these corridors, about 2000 km is already 4-lined. About 5000 km is being done or already approved now and another 4000 km is in the process of final sanction.

Ashwini Vaishnaw, Union Minister for Railways, Cabinet briefing, New Delhi

THE SEVEN HIGH-DENSITY CORRIDORS

  • Delhi-Howrah: The northern trunk toward Kolkata, already mixed with suburban and long-distance load.
  • Howrah-Mumbai: The mineral and steel spine via Kharagpur, Jharsuguda, Bilaspur and Nagpur, the home of this week’s three eastern jobs.
  • Mumbai-Delhi: The western trunk, also a Kavach 4.0 test bed.
  • Delhi-Chennai: The long diagonal, with the Ghatkesar-Kazipet job sitting on the Hyderabad approach.
  • Howrah-Chennai: The east-coast trunk, where other fourth-line jobs were cleared earlier this season.
  • Mumbai-Chennai: The southern side of the quadrilateral, including Arakkonam-Renigunta.
  • Delhi-Guwahati: The north-east trunk, not in this week’s eight-project list.

This week’s 1,196 km is therefore not the four-tracking programme. It is the slice that now has a CCEA price tag. Delhi-Howrah and Delhi-Guwahati, which run through Bihar and the north-east, are in the 11,000 km map and not in the eight funded stretches. The same briefing also restated that the Mumbai-Ahmedabad bullet train’s first 100 km, Surat to Vapi, is meant to open next year, a separate file from these freight spines.

Coalfields, Ports and a Three-Year Wait

The parties with the most cargo on the eastern tickets are collieries, steel plants, cement kilns and the ports that feed them. SECL’s Korba-Gevra-Dipka-Kusmunda-Chirimiri cluster needs a clear path west and north. Haldia and Paradip need a clear path inland. Raipur-Bhilai needs a path for finished steel. Meena’s point was that those rakes already lose the timetable argument to passenger trains on two-line sections.

In the south the extra tonnes are spread across boxes, cars, grain, fuel and fertiliser as well as bulk. Whitefield-Bangarapet’s 14.53 million tonnes on 47 km is a bet that Bengaluru’s eastern industrial and warehouse belt will keep filling trains if the tracks exist. Hosur-Omalur’s ₹263 crore logistics save is the same bet on the Tamil Nadu-Karnataka industrial strip. Arakkonam-Renigunta is the Chennai gateway on a corridor already at about 120 percent use.

Villages and temples are in both PIB notes because the alignments pass them. Bandhavgarh and Achanakmar sit on the eastern list; Tirupati, Kodaikanal and Sathyamangalam sit on the southern one. The tonnage tables still read as freight papers. Passenger relief is the by-product of a fourth path, not the unit the CCEA used to size the jobs.

What a Cabinet Nod Does Not Start

A sanction is not a tender and not steel in the ground. Contractors still have to bid. Revenue for construction firms lands years later, and only for whoever wins. The eastern human-days figure, 223 lakh, is an estimate for work that has not been let. The 2029-30 completion line is a planning horizon, not a commissioning date.

WHAT WE KNOW

  • The money: ₹20,804 crore is the combined CCEA estimate for eight named stretches, split ₹10,783 crore and ₹10,021 crore.
  • The dates: both releases say the jobs are planned to be completed up to 2029-30.
  • The HDN split: Vaishnaw’s briefing put about 2,000 km as already four-lined, 5,000 km on or approved, and 4,000 km in last sanction.

WHAT IS UNCONFIRMED

  • Tender timing: neither release names when bids will be called or which zones will let which packages.
  • Kazipet freight: the 110 km Telangana job has a cost from Kishan Reddy and no public extra-tonnage figure of its own.
  • The remaining 4,000 km: which exact HDN sections sit in the last-sanction bucket has not been published as a stretch list with this package.

If the 2029-30 dates hold, the first extra 74 million tonnes from these eight jobs arrive in the same window as the rest of the four-tracking queue. Until then the Howrah-Mumbai mineral spine and the southern industrial feeders keep running past 100 percent on the tracks they already have.

Harry is the editor of COVER 365, an independent publication he owns and runs, and a journalist of ten years who moved from reporting into editing. Anything the site reviews has been used before it is judged. A phone, a car, a game or a piece of travel gear is tested in ordinary conditions, its measured results are set against the maker's specification sheet, and where the two disagree the article says which one to trust and why. No product gets a verdict Harry has not earned by using it. Off the test bench, the same rule of primary evidence applies: business stories come from filings and results, science from the published paper, sports from the governing body's records, and news from statements and transcripts rather than second hand accounts. Coverage runs across technology, auto, gaming, lifestyle and travel as well as news, business, science, sports and entertainment, for readers in every part of the world. Every figure is checked before publication and corrected publicly under a stated policy when wrong. Reader mail is answered at support@cover365.in.